Enabling Drilling on DP at 379m Water Depth and Harsh Environment in the North Sea

THE QUICK OVERVIEW

WHO: An established 4Subsea customer operating in the North Sea, facing a disagreement with its drilling contractor over whether mooring or DP should be used for rig station keeping.

WHAT: A DP Feasibility Study comparing mooring and DP options.

WHERE: The Norwegian Continental Shelf (NCS), in a harsh offshore environment at approximately 379 metres water depth.

HOW: A tailored engineering assessment identified operational limitations and provided a technical basis for discussions with the drilling contractor and subsequent risk assessments.

WHY: To determine whether DP could provide a technically viable alternative to mooring, potentially simplifying offshore operations and reducing the time and costs associated with anchor handling.

OUTCOME: DP operations were subsequently carried out, and the well was drilled successfully, with no incidents reported.

A DP Feasibility Study helped an operator move beyond the initial assumption of conventional mooring and progress towards a successful DP drilling campaign.


Background

An operator planning a well offshore Norway faced an important decision. At approximately 379 metres water depth, the initial assumption was that the operation would require conventional mooring. However, the operator was aware of other projects worldwide where DP had been used at comparable or even shallower water depths and wanted to understand whether a similar approach could be justified for this well. The operator approached 4Subsea to assess the candidate rig configurations, determine which offered the best prospects for DP operations, and identify any required mitigation measures. The assessment would provide the operator with a technical basis for discussions with the drilling contractor while there was still flexibility to influence the proposed operating concept.

Challenges

Water depth alone was not sufficient to determine whether DP was feasible. The decision required an assessment of the specific well location and candidate rig configurations, including the loads transferred through the drilling riser and BOP to the wellhead and conductor. The operator also needed a sound technical basis for discussions with the drilling contractor. Moving beyond the initial mooring assumption required alignment on the engineering findings, as well as an understanding of the additional analyses and risk assessments needed to progress with DP.

Solution

The DP assessment used a realistic drift-off representation, incorporating a fully coupled model that accounts for riser restoring effects to better represent actual vessel behaviour during a blackout event. By capturing positive transient effects that are often overlooked in simplified approaches, the methodology enables more accurate and operationally optimised disconnect and alert limits. The study provided an engineering basis for evaluating the DP option and discussing it with the drilling contractor. The contractor’s existing relationship with 4Subsea for riser analysis also helped align the technical dialogue between the operator, contractor, and engineering team, supporting the subsequent evaluations and risk assessments.

The feasibility study served as an early decision-support tool. Its findings informed the further engineering and operational assessments required to execute the project. The study itself was not a substitute for detailed riser and conductor analyses or formal operational acceptance.

Results

  • DP operation confirmed: The rig operated in DP, avoiding the need for mooring during the reported operation.
  • Better-informed contractor discussions: The findings provided the operator with a technical basis for introducing DP as an alternative to the drilling contractor and aligning the subsequent engineering evaluations and risk assessments.
  • Successful well delivery: The well was drilled successfully, with no incidents reported.
  • Time and cost benefits: Avoiding anchor deployment and retrieval reduced associated offshore activities, operational complexity, and project costs.

Conclusion

The DP Feasibility Study provided a practical engineering basis that helped the operator progress the DP concept with the drilling contractor. The outcome was a successful DP operation and a well drilled without reported incidents. Avoiding conventional mooring simplified offshore operations and reduced project costs.

The case illustrates the value of assessing DP feasibility while rig selection and contracting decisions are still being considered. A location- and rig-specific study can reveal a viable operating option, identify the mitigation measures it depends on, and guide the engineering and risk assessments needed to move towards execution.